Salix Court Site Set Up

On this page you can:

  • Hear the letter read out, usually in your preferred language.
  • Read the letter in your preferred language
  • Read the letter using different fonts or colours
  • Download and print the original letter
  • Get more detail about the letter

To see or hear the letter in your preferred language:

  • Press the ReciteMe button at the bottom of the the screen (bottom left if on a laptop or desktop computer)
  • On the toolbar that appears, select your preferred language. Languages with a speaker icon will also read it in that language. You can also select preferred font and colours if that helps you read it.
  • Reload this page
  • On the toolbar, press the play button
  • Move down to where it says “Letter text” and click.
  • Click on each line to hear it read out

THE KEY POINTS FROM THE LETTER:

• 23rd August 2021 work will begin on Salix Court.
• All work will take place between 8AM & 5PM
• car parking spaces currently in use will remain unaffected.
• Noise and vibration levels will be high throughout.
• You may be asked by a Banksman to use an alternative entrance / Exit.

 

Letter Text

26th July 2021

Dear Resident

28 Day Notice Salix Court site set up

As part of the programme of PTOL Site team will be undertaking site set up works to Salix Court.

The site set up are what needs to be done to make the building ready for further work to your block.

Below is a breakdown of the site set up that will start 23/08/2021 and take around 6 weeks.

• Construction of temporary heras fencing.
• A site generator will be positioned by the fence adjacent Whitebeam Close.
• Support anchors will be drilled into the concrete structure
• Mast-climbers will be installed around the building
• Scaffolding will be installed around the building up to the first-floor level.

If you would like more detail about the type of work carried out please see visit:
https://www.pendletontogether.co.uk/salix-site-set-up

All PTOL personnel and contractors working on our behalf will be carrying an identification card. All PTOL personnel and contractors will be working within government guidelines for a Covid safe work environment. If you have any concerns about a contractor, please contact your resident liaison officer at once.

We hope this won’t cause you any distress, if you have any concerns, please don’t hesitate to contact me. I know that some residents will want more detail. This is available at https://www.pendletontogether.co.uk/salix-site-set-up

Yours sincerely

Stephen Sloane
Resident Liaison Coordinator

Download Letter as PDF

You can download the letter as a PDF file by clicking here.

Further Detail

SALIX

Mast climbers & scaffold installation 28 day notice

Dates, duration and working hours
Mast-climbers: Start 23rd August 2021 for 4 weeks.
Scaffold: Start w/c 30th August 2021 for 4 weeks
Works will be carried out within the agreed times of 08.00 to 17.00.

Purpose for the work.
The intention on Salix is to use public protection scaffolding and mast climbers with associated
working platforms to allow access for the proposed cladding works on all elevations.

What work is involved.
Enabling works will commence on the 23rd August 2021 and will involve the construction of
temporary heras fencing around the perimeter creating a fence line & safe demarcation zones for
workers and residents.

A site generator will be positioned on the hardstanding area adjacent the fence on Whitebeam
Close. A banksman/marshal shall be present on site for the duration of all works to direct and assist
residents.

Mast-climbers and scaffold deliveries will be managed to cause minimal disruption and equipment
will be stored on the ground in secured locations on site. The climber installation will be phased
around the building starting on the rear elevation and working around to the front elevation on
Whitebeam Close.

Scaffolding and hoarding works to the working platform will follow the same phasing as the mastclimber
installation. The working platform will be set at first floor level. These works should be
complete by early October 2021.

While these works are carried out to the front and rear elevations residents will be directed either to
the front or rear entrances respectively and this will be continually monitored by a
banksman/marshal.

All car parking spaces currently in use will remain unaffected. None of the areas we take possession
of will adversely affect bin collections, dry riser or any other services associated with the block.
How will this affect us.

Support anchors will be drilled into the concrete structure and it is anticipated that noise and
vibration levels associated with this work will be higher than that experienced so far due to the tools
and equipment required for works of this type.

Access for the residents, bin collections and the emergency services will be maintained throughout
the works.