LAST UPDATED: Monday 22nd November 2021

Please check for general announcments or for information specific to your block below.

General Announcements

July 2021

  • 28-day notice for Plane access works to be issued to residents Monday
  • 7-day notice for Hornbeam drainage works to be issued to residents Monday
  • Spruce, Thorn, Hornbeam, Whitebeam and Salix – cleaners power supply requested to be turned on between 0830 and 1600 hours.

June 2021

  • Hornbeam, Whitebeam & Spruce- cleaners power switched on to all floors 9am to 4pm

April 2021

CCTV Drainage surveys have been delayed for all blocks until the week commencing 19th April

January 2021

Holm Court / Plane Court residents – please be aware that work will be commencing on Monday 25th January which will involve the closure of the gable end to Holm Court facing Brotherton House.  This will be between the hours of 8am and 5pm and will be for 1 week

From 25th January, for 3 weeks – 2 parking spaces will be required on Holm Court car park at different intervals.  Please see the diagram on the notice board for details of which spaces will be required

 

December 2020

Beech court residents, please be aware that  during the week commencing 14th December it will be necessary to close pedestrian access to the gable end facing Belvedere Road between the hours of 8am and 5pm.

 

Reminder of asbestos removal work taking place on Thorn, Spruce and Plane Court (unit 4)

This will affect Thorn on Monday 7th December – floor 11

Spruce Court on Tuesday and Wednesday the 8th and 9th affecting floors 6, 8 and communal ground

Plane Court (unit 4) the 11th December

 

September 2020

Please be aware that from the week commencing 14/09/20, the pedestrian gate to Holm Court from the public car park will be out of use Monday to Friday, between the hours of 8am and 5pm August 2020

August 2020

Please be advised that a small welfare facility for contractors is being established in The Square from 19/08/20.  This will be located as far away from the blocks as possible -this will be in the fenced area next to Salix / opposite Whitebeam.  This will not affect car parking.

Spruce Court

Got any questions? Ask Emma, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updates:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.
  • Installation of public protection scaffold

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

15th November:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • Affecting all areas floors 20,21 &22

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

8th November:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering. Affecting all areas floors 20,21 &22

1st November:

  • Brick knock outs
  • Concrete repairs
  • SHS & associated works
  • PE – door surveys
  • Jacobs external surveys
  • Roofdec external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering. High noise levels will affect all properties to floors 19, 20, 21 & 22

October 2021 Weekly Updates:

W/C 25th October:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • PE – door surveys
  • Jacobs external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 18th October:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • PE – door surveys
  • Jacobs external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 11th October:

  • Brick remedial works
  • SHS associated works
  • PE – door surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 4th October: 

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

September 2021 Weekly Updates:

W/C 27th September:

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 20th September:

  • Brick remedial works
  • SHS associated works *

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 13th September:

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 6th September:

  • SHS steel installation
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Installation of dropdowns to mast climbers

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

August 2021 Weekly Updates:

W/C 31st August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • SHS steel works

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 23rd August:

  • Slab edge repairs
  • Steal rod installation
  • Preliminary temp work
  • Remedial works to MCWP ties*
  • SHS steel works

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 16th August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • SHS steal works

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 9th August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • SHS steal works

These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 2nd August:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys, communal power required
  • Non intrusive visual sprinkler survey

These works will involve increased levels of noise in line with industry standards due to the associated drilling, grinding, and hammering

July 2021 Weekly Updates

W/C 26th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 19th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys
  • Installation of data units to PV’s

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 12th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys
  • Additional external lighting 2no

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 5th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys
  • Additional external lighting 2no

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

June 2021 Weekly Updates

W/C 28th June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys
  • Additional external lighting 2no

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 21st June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Wyse power testing
  • Door surveys

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 14th June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts *
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • PTSG – testing
  • Wyse power testing
  • Door surveys
  • Roof surveys – PV panels

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 7th June: 

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Fixing pull tests
  • Mast climber tie installation
  • Mastclimber adaptions
  • Remedial works to MCWP ties*
  • Works associated with SHA steels
  • Internal door survey

These works will involve increased levels of noise due to the associated drilling, grinding and hammering

May 2021 Weekly Updates

W/C 31st May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts *
  • Remedial works to MCWP ties*
  • PTSG – testing
  • Wyse power testing

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 24th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts *
  • Works to roof PV panels
  • Remedial works to MCWP ties*

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 17th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts *
  • SGB six monthly MCWP inspections
  • Remedial works to MCWP ties*

* These works will involve increased levels of noise due to the associated drilling,  grinding and hammering

W/C 10th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts
  • Pick Everard roof survey

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 3rd May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

April 2021 Weekly Updates

W/C 26th April:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • CCTV drainage surveys
  • Internal 3D surveys – flats & communal areas
  • 7 Day Notification: PV Electrical Works

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 19th April:

  • Installation of fixings to window pods. *

(This process consists of 6 separate drilling points. You will experience internment drilling and noise levels while this is completed)

  • Installation of brick ties. *
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.
  • Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 12th April:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Internal 3D surveys – flats & communal areas

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

W/C 5th April:

  • Internal fire alarm surveys
  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Steel work letter

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

March 2021 Weekly Updates

W/C 29th March:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests

 

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering *

W/C 22nd March: 

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • RPS external survey to front elevation.
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

*These works will involve increased levels of noise due to the associated drilling.

W/C 15th March:

  • Installation of fixings to window pods. *
  • Installation of brick ties. *
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.
  • Roof condition survey by Pick Everard.

 

* Please note these works will involve increased levels

W/C 8th March:

  • Installation of canopies to mast climbers.
  • Installation of fixings to window pods. *
  • Installation of brick ties.
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.
  • Roof condition survey by Pick Everard.

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 1st March:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Flat 207 – Internal repairs and making good.
  • Flat 207 – external intrusive surveys of SFS
  • Sample concrete repairs to floor slab edges
  • Installation of fire marshal viewing windows to hoarding.
  • Installation of ply to close gap between working platform & building

February 2021 Weekly Updates

W/C 22nd February:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Flat 207 intrusive brick tie investigation and making good –
  • will involve drilling and hammering.
  • Sample concrete repairs to floor slab edges
  • Installation of ply to close gap between working platform & building

W/C 15th February:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Flat 207 intrusive brick tie investigation and making good – will involve drilling and hammering.
  • Sample concrete repairs to floor slab edges
  • Installation of ply to close gap between working platform & building

W/C 8th February:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Sample concrete repairs to floor slab edges
  • Installation of ply to close gap between working platform & building

W/C 1st February: 

  • Installation of canopies to mast climbers
  • Parapet surveys – PE
  • Installation of canopies over entrance doors
  • Installation of ply to close gap between working platform & building

January 2021 Weekly Updates

W/C 25th January:

  • Installation of canopies to mast climbers
  • Lift housing surveys – PE & Windtec
  • Installation of ply to close gap between working platform & building

 

W/C 4th January:

  • Surveys of communal areas by RPS contractors
  • Internal riser doors by contractors – Truline.
  • Temporary enabling works for steel box section installation

December 2020 Weekly Updates

W/C 14th December

  • ARD air brick removal
  • Brick work remediation continues, this will involve drilling and grinding works
  • Surveys to communal areas
  • External window pod surveys
  • Wintec parapit survey
  • Connection of temporary site lights to landlord’s supply

W/C 7th December

  • ARD air brick removal
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Surveys to communal areas
  • External window pod surveys
  • ARD will be carrying out asbestos removal work on floors 8 and 6 on Tuesday and Wednesday. Notifications have been sent to all properties outlining details .  2 parking spaces will also be needed for the set up of a decontamination unit
  • Wintec parapit survey
  • Truline – decorating riser door frames & fitting smoke seals

November 2020 Weekly Updates 

W/C 30th November

  • ARD air brick removal
  • Brick work remediation continues, this will involve drilling and grinding works.
  •  Surveys to communal areas
  • External window pod surveys
  • Removal of external hoarding to pump room

W/C 23rd November

  • ARD air brick removal
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Surveys to communal areas
  • External window pod surveys
  • Capping surveys
  • External window pod surveys
  • Removal of external hoarding to pump room

W/C 9th November

  • External point scan surveys continue.
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Surveys to communal areas
  • Works to lightening conductors – PTSG
  • Concrete testing, floor slabs – will involve drilling
  • Internal surveys, communal areas – Argos
  • External surveys PE/Wintec CP, SFS & curtain walling inspections
  • Asbestos removal from pump room – two parking spaces required

 

W/C 2nd November

  • External surveys continue.
  • Brick work remediation continues
  • Surveys to communal areas
  • Works to lightening conductors
  • Air brick removal
  • Concrete testing in floor slabs
  • Works to lightening conductors
  • Internal surveys of communal areas
  • Two parking spaces will be taken up due to work in the pump room

W/C 26th October:

  • External surveys continue.
  • Brick work remediation continues
  • Localised removal of brick work to allow inspections
  • Internal surveys of risers
  • Works to lightening conductors
  • Clear out of Bin stores, garages, plantrooms
  • Concrete testing, floor slabs
  • Roof caping removal

September 2020

 

W/C 14th September: 

  • External Surveys continue 
  • Brick work remediation continues – this does involve drilling and grinding work 
  • Survey of lift housing antenna 
Thorn Court

Got any questions? Ask Christine, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

 

November 2021 Weekly Updates:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.
  • Installation of public protection scaffold

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

15th November:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • Affecting all areas floors 20,21 &22

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

8th November:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering. Affecting all areas floors 20,21 &22

1st November:

  • Brick knock outs
  • Concrete repairs
  • SHS & associated works
  • PE – door surveys
  • Jacobs external surveys
  • Roofdec external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering. High noise levels will affect all properties to floors 19, 20, 21 & 22

October 2021 Weekly Updates:

W/C 25th October:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • PE – door surveys
  • Jacobs external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 18th October:

  • Brick knock outs
  • Concrete repairs
  • SHS & assosiated works
  • PE – door surveys
  • Jacobs external surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 11th October:

  • Brick remedial works
  • SHS associated works
  • PE – door surveys

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 4th October: 

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

September 2021 Weekly Updates:

W/C 27th September:

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 20th September:

  • Brick remedial works
  • SHS associated works *
  • Internal decoration to entrance following water ingress

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 13th September:

  • Brick remedial works
  • SHS associated works

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

W/C 6th September:

  • SHS steel installation
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Installation of dropdowns to mast climbers

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

August 2021 Weekly Updates:

W/C 31st August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Brickwork installation

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 23rd August:

  • Slab edge repairs
  • Steal rod installation
  • Preliminary temp work
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Brickwork installation
  • Removal of loose insulation from floor of pump room

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 16th August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Visual asbestos survey in pump room

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 9th August:

  • Slab edge repairs
  • Steal rod installation
  • Perlimanary temp work
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Visual asbestos survey of pump room

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

W/C 2nd August: 

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys, communal power required
  • Non intrusive visual sprinkler survey

These works will involve increased levels of noise in line with industry standards due to the associated drilling, grinding, and hammering

July 2021 Weekly Updates

W/C 26th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 19th July :

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys
  • Installation of data units to PV’s

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 12th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 5th July:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Door surveys

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

June 2021 Weekly Updates

W/C 28th June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 21st June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Wyse power testing

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 14th June:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts*
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • PTSG – testing
  • Wyse power testing
  • Roof surveys – PV panel

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 7th June: 

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Fixing pull tests
  • Mastclimber tie installation
  • Mastclimber adaptions
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.

These works will involve increased levels of noise due to the associated drilling, grinding and hammering

May 2021 Weekly Updates

W/C 31st May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts*
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • PTSG – testing
  • Wyse power testing

These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 24th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts*
  • SGB six monthly MCWP inspections
  • Remedial works to MCWP ties*
  • Works associated with SHS steels.
  • Works to roof PV panels

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 17th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts*
  • SGB six monthly MCWP inspections
  • Remedial works to MCWP ties*

* These works will involve increased levels of noise due to the associated drilling,  grinding and hammering

W/C 10th May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Mast climber tie knockouts
  • Pick Everard roof survey

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 3rd May:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

April 2021 Weekly Updates

W/C 26th April:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • CCTV drainage surveys
  • Internal 3D surveys – flats & communal areas
  • 7 Day Notification: PV Electrical Works

* These works will involve increased levels of noise due to the associated drilling, grinding and hammering

W/C 19th April:

  • Installation of fixings to window pods. *

(This process consists of 6 separate drilling points. You will experience internment drilling and noise levels while this is completed)

  • Installation of brick ties. *
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 12th April:

  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

W/C 5th April:

  • Internal fire alarm surveys
  • Installation of canopies to mast climbers – should be complete by Friday 2nd April
  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • Steel work letter

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

March 2021 Weekly Updates

W/C 29th March:

  • Installation of canopies to mast climbers – should be complete by Friday 2nd April
  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests

 

* These works will involve increased levels of noise due to the associated drilling,

grinding and hammering

W/C 22nd March:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods *
  • Installation of brick ties *
  • Remedial works to cement board and SFS *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

* These works will involve increased levels of noise due to the associated drilling.

W/C 15th March:

  • Installation of canopies to mast climbers.
  • Installation of fixings to window pods. *
  • Installation of brick ties. *
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.
  • Roof condition survey by Pick Everard.

 

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 8th March:

  • Installation of canopies to mast climbers.
  • Installation of fixings to window pods. *
  • Installation of brick ties.
  • Remedial works to cement board and SFS. *
  • Brick tie investigations – will involve the localised removal of brick work.
  • Fixing pull tests.
  • Roof condition survey by Pick Everard.

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 1st March:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Sample concrete repairs to floor slab edges – will involve drilling and grinding
  • Box steel installation prep works

February 2021 Weekly Updates

W/C 22nd February:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Sample concrete repairs to floor slab edges
  • Installation of ply to close gap between working platform & building

W/C 15th February: 

  • Installation of canopies to mast climbers
  • Trueline – installation of fire doors floors 14 & 9.
  • Trueline – installation of smoke seals to risers all floors
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Sample concrete repairs to floor slab edges
  • Improvements to canopies over entrance doors
  • Installation of ply to close gap between working platform & building

W/C 8th February:

  • Installation of canopies to mast climbers
  • Installation of fixings to window pods
  • Brick tie investigations – will involve the localised removal of brick work.
  • Sample concrete repairs to floor slab edges
  • Improvements to canopies over entrance doors
  • Installation of ply to close gap between working platform & building

W/C 1st February:

  • Installation of canopies to mast climbers
  • Parapet surveys – PE
  • Installation of canopies over entrance doors
  • Installation of ply to close gap between working platform & building

January 2021 Weekly Updates

W/C 25th January:

  • Installation of canopies to mast climbers
  • Lift housing surveys – PE & Windtec
  • ARD surveys
  • Installation of ply to close gap between working platform & building

W/C 4th January:

  • Surveys of communal areas by contractors – RPS
  • Internal riser doors by contractors Truline
  • Temporary enabling works for steel box section installation

December 2020 Weekly Updates

W/C 14th December

  • ARD air brick removal
  • Pilot steel installation
  • External window pod surveys
  • Wintec parapit survey
  • Connection of temporary site lights to landlord’s supply
  • Flat 58 (Void property) – Making good

W/C 07th December

  • ARD air brick removal
  • Pilot steel installation works
  • External window pod surveys
  • Wintec parapit survey
  • Asbestos removal to risers, floor 11 – Monday
  • Flat 58 (void property) – enabling works and surveys

November 2020 Weekly Updates

W/C 30th November

  • ARD air brick removal
  • Pilot steel installation
  • External window pod surveys
  • Flat 58, void property enabling works and surveys

W/C 23rd November

  • ARD air brick removal
  • Capping surveys 
  • Pilot steel installation
  • External window pod surveys
  • Scaffolding work, there will be a wagon on site.  Parking spaces will not be affected by this

W/C 16th November

  • External point scan surveys continue.
  • External surveys & curtain walling inspections
  • Pilot steel installation
  • External window pod surveys
  • Scaffolding work, wagon on site.
  • Concrete testing, floor slabs – will involve drilling
  • Works to lightening conductors – PTSG

W/C 9th November

  • External point scan surveys continue.
  • External surveys PE/Wintec CP, SFS & curtain walling inspections
  • Pilot steel installation
  • Internal surveys, communal areas – Argos
  • Scaffolding work, wagon on site.
  • Concrete testing, floor slabs – will involve drilling
  • Works to lightening conductors – PTSG

W/C 2nd November

  • External surveys continue.
  • Pilot steel installation continues
  • Internal surveys of communal areas
  • Concrete testing in floor slabs
  • Works to lightening conductors

October 2020

W/C 26th October

  • External surveys continue.
  • Pilot steel installation
  • Localised removal of brick work to allow inspections
  • Internal surveys of risers
  • Concrete testing in floor slabs
  • Works to lightening conductors –

September 2020

W/C 14th September: 

  • External Surveys continue 
  • Brick work remediation continues – this does involve drilling and grinding work 
  • Survey of lift housing antenna 
Malus Court

Got any questions? Ask Paul, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

 

November 2021 Weekly Updaters:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

15th November:

  • No updates this week

8th November:

  • No updates this week

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • PE – door surveys

W/C 18th October:

  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • No updates this week

September 2021 Weekly Updates:

W/C 27th September:

  • No updates this week

W/C 20th September:

  • No updates this week

W/C 13th September:

  • No updates this week

W/C 6th September:

  • No updates this week

August 2021 Weekly Updates:

W/C 31st August:

  • No updates this week

W/C 23rd August:

  • Removal of loose insulation from floor of pump room
  • Removal of loose insulation from floor from garage

W/C 16th August:

  • Ground investigation, sprinkler tank, core drilling in garage
  • Visual asbestos survey in pump room

W/C 9th August:

  • Visual asbestos survey of pump room

W/C 2nd August:

  • Non intrusive visual sprinkler survey

July 2021 Weekly Updates

W/C 26th July:

  • Repair to underground cable

W/C 19th July:

  • Mast climber installation
  • Installation of data units to PV’s
  • Repair to underground cable

W/C 12th July:

  • PE Floor slab concrete testing
  • Capping strapping inspection
  • Fire Door Survey

W/C 5th July:

  • Brick tie investigations – will involve the localised removal of brick work.
  • Capping strapping inspection

June 2021 Weekly Updates

W/C 28th June:

  • Asbestos removal to garages
  • Scaffolding works for asbestos removal
  • Fire Door Survey

W/C 21st June:

  • Asbestos removal to garages
  • Excavation of damaged gate duct/cable
  • Scaffolding works for asbestos removal

W/C 14th June:

  • Roof surveys – PV panels
  • Asbestos removal to garages
  • Excavation of damaged gate duct/cable
  • Scaffolding works for asbestos removal

W/C 7th June:

  • Asbestos removal to garages
  • Black tie investigations – will involve the localised removal of brick work
  • Scaffolding works for asbestos removal

May 2021 Weekly Updates

W/C 31st May:

  • Asbestos removal to garages
  • Scaffolding works for asbestos removal

W/C 24th May:

  • Asbestos removal to garages
  • PE internal survey of risers/service cupboards

W/C 17th May:

  • Erection of scaffold hoarding to garages
  • Door surveys
  • Works to roof PV panels

W/C 10th May:

  • Works to roof PV panels
  • Pick Everard roof survey
  • Pre entry surveys continue

W/C 3rd May:

  • Pre entry surveys continue

April 2021 Weekly Updates

W/C 26th April

  • Pre entry surveys continue
  • Day Notification: PV Electrical Works

W/C 19th April:

  • Pre-Entry Surveys.
  • Fire door Surveys. *
  • CCTV drainage surveys *
  • 28 day notice – Asbestos removal letter

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 12th April:

  • Waterproofing of front elevation on going

W/C 5th April:

  • Internal 3D surveys
  • Waterproofing of front elevation on going
  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed
  • Concrete testing to floor slab edge elevations A&B

March 2021 Weekly Updates

W/C 29th March:

  • Waterproofing of front elevation on going
  • External survey, removal of localised sections of cembrit to photograph and measure
  • steel & SFS, board to be replaced and resealed
  • Concrete testing to floor slab edge

W/C 22nd March:

  • Waterproofing of front elevation
  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Waterproofing of front elevation.
  • Roof condition survey by Pick Everard.
  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed.
  • External surveys by Site Survey Systems.

W/C 8th March:

  • Waterproofing of front elevation will take 4 to 5 weeks.
  • Site survey systems – external surveys

W/C 1st March:

  • Waterproofing of front elevation will take 4 to 5 weeks
  • 7-day inspection of parapet capping

February 2021 Weekly Updates 

W/C 22nd February:

  • Waterproofing of front elevation will take 4 to 5 weeks
  • PTSG – lightening conductor tests
  • 7-day inspection of parapet cappings
  • Concrete surveys to floor slab edge, will involve drilling
  • 7-day notice letter – Weatherproofing

W/C 15th February: 

  • PTSG – lightening conductor tests
  • Concrete surveys to floor slab edge, will involve drilling

W/C 8th February:

  • PTSG – lightening conductor tests
  • Water ingress repairs

W/C 1st February:

  • Lift housing surveys – PE & Windtec
  • ARD removals – Lift motor rooms core 2&3 & RPS inspections
  • PTSG – lightening conductor tests
  • RPS external surveys
  • Temporary strapping installation to roof cappings – all elevations

January 2021 Weekly Updates

W/C 25th January:

  • Lift housing surveys – PE & Windtec
  • ARD surveys
  • PTSG – lightening conductor tests
  • Temporary strapping installation to roof cappings – all elevations

Decemeber 2020 Weekly Updates

W/C 14th December

  • Asbestos surveys to communal areas
  • Wintec parapit survey
  • Non intrusive surveys
  • External window pod surveys

W/C 07th December

  • Asbestos surveys to communal areas
  • Wintec parapit survey
  • External window pod surveys

November 2020 Weekly Updates

W/C 30th November

  • Surveys to communal areas
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Footpath closure to Whitebeam gable.
  • External window pod surveys
  • Brick slip investigation and planning

W/C 23rd November

  • Surveys to communal areas
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Footpath closure to Whitebeam gable end
  • External window pod surveys
  • Capping invstigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • Surveys to communal areas
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Footpath closure to Whitebeam gable.
  • External window pod surveys
  • External surveys & curtain walling inspections

W/C 9th November

  • Surveys to communal areas
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Internal surveys, communal areas – Argos
  • Flat 11 – making good works
  • External surveys PE/Wintec CP, SFS & curtain walling inspections

W/C 2nd November

  • Surveys in communal areas
  • Brick work remediation continues
  • Celotex removal in some specific garages
  • External surveys

October 2020

W/C 26th october

  • Surveys to bin stores, garages, plantrooms continue
  • Internal surveys in pump and plant rooms
  • External surveys

September 2020

 

W/C 14th September

  • Removal of scaffold continues
  • Repair of scaffold ties
  • Survey of lift housing antenna
Salix Court

Got any questions? Ask Ben, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updaters:

22nd November:

  • Installation of wall ties
  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering.

15th November:

  • Erection of scaffolding – this will involve drilling scaffolding ties into the floor slab edges

8th November:

  • Ground plate bearing tests
  • Erection of scaffolding – this will involve drilling scaffolding ties into the floor slab edges

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • PE – door surveys

W/C 18th October:

  • Truline door surveys
  • Grass cutting & litter pick
  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • No updates this week

September 2021 Weekly Updates:

W/C 27th September:

  • No updates this week

W/C 20th September:

  • Grass cutting and litter picking behind heras fencing

W/C 13th September:

  • No updates this week

W/C 6th September:

  • No updates this week

August 2021 Weekly updates

W/C 31st August:

  • No updates this week

W/C 23rd August:

  • Removal of loose insulation from floor of pump room

W/C 16th August:

  • Ground investigation, sprinkler tank, core drilling in garage
  • Visual asbestos survey in pump room

W/C 9th August:

  • Visual asbestos survey of pump room

W/C 2nd August:

  • Door surveys, communal power required
  • Non intrusive visual sprinkler survey

July 2021 Weekly Updates

W/C 26th July:

  • Door surveys

W/C 19th July:

  • Door surveys
  • Grass maintenance
  • Installation of data units to PV’s

W/C 12th July:

  • PE Floor slab concrete testing
  • Door surveys
  • Grass maintenance
  • Capping strapping inspection

W/C 5th July:

  • Scaffolding removal works for asbestos removal
  • Door surveys
  • Capping strapping inspection

June 2021 Weekly Updates:

W/C 28th June:

  • Slab edge surveys
  • Scaffolding works for asbestos removal
  • Asbestos removal to garages

W/C 21st June:

  • Asbestos removal to garages

W/C 14th June:

  • Roof surveys – PV panels
  • Asbestos removal to garages
  • Scaffolding works for asbestos removal

W/C 7th June:

  • Door Surveys
  • Brick tie investigations – will involve the localised removal of brick work
  • Scaffold to garages

May 2021 Weekly Updates

W/C 31st May:

  • Door surveys
  • Brick tie surveys and pull out tests to slab edge

W/C 24th May:

  • Brick tie surveys and pull out tests to slab edge

W/C 17th May:

  • Works to roof PV panels
  • Brick tie surveys and pull out tests to slab edge

W/C 10th May:

  • Pick Everard roof survey
  • Brick tie surveys and pull out tests to slab edge

W/C 3rd May:

  • Brick tie surveys and pull out tests to slab edge

April 2021 Weekly Updates

W/C 26th April:

  • CCTV drainage surveys
  • Brickwork surveys
  • 7 Day Notification: PV Electrical Works

W/C 19th April:

  • Brickwork surveys. *
  • 28 day notice – Asbestos removal letter

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 12th April:

  • Internal 3D surveys – flats & communal areas

W/C 5th April:

  • No New updates this week

March 2021 Weekly Updates

W/C 29th March:

  • No new updates this week

W/C 22nd March:

  • Mastic sealing to ground floor doors and windows
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Mastic sealing to ground floor doors and windows.
  • External surveys by Site Survey Systems.
  • Roof condition survey by Pick Everard.

W/C 8th March:

  • Mastic sealing to ground floor doors and windows.
  • Temporary strapping installation to roof cappings.
  • Site survey systems – external surveys.
  • Wintech intrustive external surveys to all floors

W/C 1st March:

  • Mastic sealing to ground floor doors and windows
  • Temporary strapping installation to roof cappings
  • 7-day inspection of parapet cappings

February 2021 Weekly Updates

W/C 22nd February:

  • Mastic sealing to ground floor doors and windows
  • Temporary strapping installation to roof cappings
  • 7-day inspection of parapet cappings
  • Brick surveys
  • Closure of ped gate Lombardy gable – 8am- 5pm. Full time banksman in attendance

W/C 15th February:

  • PTSG – lightening conductor tests
  • Concrete surveys to floor slab edge, will involve drilling

W/C 8th February:

  • Capping remedial works
  • Temporary strapping installation to roof cappings
  • Brick surveys
  • Remedial groundworks commence
  • Closure of ped gate Lombardy gable – 8am- 5pm. Full time banksman in attendance

W/C 1st February:

  • Surveys – PE & Windtec
  • Temporary strapping installation to roof cappings – all elevations
  • Brick surveys
  • Concrete testing – will involve drilling
  • PTSG – lightening conductor tests
  • RPS external surveys
  • Closure of ped gate Lombardy gable – 8am- 5pm. Full time banksman in attendance

January 2021 Weekly Updates

W/C 25th January:

  • Lift housing surveys – PE & Windtec
  • Temporary strapping installation to roof cappings – all elevations
  • Brick surveys
  • Concrete testing – will involve drilling
  • Closure of ped gate Lombardy gable – 8am- 5pm. Full time banksman in attendance

December 2020 Weekly Updates

W/C 14th December

  • Asbestos surveys to communal areas
  • External window pod surveys
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Closure of ped gate Lombardy gable 8.00 to 17.00 – Manned alternative route

W/C 07th December

  • Asbestos surveys to communal areas
  • External window pod surveys
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Closure of ped gate Lombardy gable 8.00 to 17.00 – Manned alternative route 7th December

November 2020 Weekly Updates

W/C  30th November

  • Surveys to communal areas
  • External window pod surveys
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Brick slip investigation and planning

W/C 23rd November

  • Surveys to communal areas
  • ARD – airbrick removal
  • External window pod surveys
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Closure of ped gate Lombardy court 8am-5pm. Site marshals will be available to re direct pedestrians
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • Airbrick removal
  • External window pod surveys
  • Brickwork surveys
  • Flat 27 – making good following survey

W/C 9th November

  • Internal surveys, communal areas – Argos
  • Flat 27 – surveys  

W/C 2nd November 2020

  • Surveys in communal areas

October 2020

W/C 26th october

  • Surveys in bin stores, garages, plantrooms

September 2020

W/C 14th September

  • Survey of lift housing antenna
  • External surveys continue
Hornbeam Court

 

Got any questions? Ask Danielle, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updaters:

22nd November:

  • Adaptions to scaffolding to allow access to the community room (potential)
  • Erection of covered pedestrian walkway (potential).
  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering.

15th November:

  • Installation of temporary works to cables affecting all areas floors 10 & 11.
  • Adaptions to scaffolding to allow access to the community room (potential)
  • Erection of covered pedestrian walkway (potential).

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

8th November:

  • Installation of temporary works to cables affecting all areas floors 10 & 11.

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • Alterations to scaffold to allow access to community room
  • PE – door surveys

W/C 18th October:

  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • Fire door surveys

September 2021 Weekly Updates:

W/C 27th September:

  • Front fire door survey

W/C 20th September:

  • External surveys PE

W/C 13th September:

  • Brick tie remedials

W/C 6th September:

  • Installation of wall ties

August 2021 Weekly Updates:

W/C 31st August:

  • Wall tie installation

W/C 23rd August:

  • Wall tie installation w.c

W/C 16th August:

  • Ground investigation, sprinkler tank, core drilling in future tank room
  • Fire alarm commisioning if able to co-ordinate with Mite, date TBC

W/C 9th August:

  • No updates this week

W/C 2nd August: 

  • Door surveys, communal power required
  • Installation of external bulkhead lighting
  • Non intrusive visual sprinkler survey

July 2021 Weekly updates

W/C 26th July:

  • Door surveys
  • Painting of hoarding

W/C 19th July:

  • Painting of hoarding
  • Grass maintenance
  • Installation of data units to PV’s
  • lighting installation to hoarding

W/C 12th July:

  • PE Floor slab concrete testing
  • Erection of hoarding
  • Grass maintenance
  • Drainage repairs

W/C 5th July:

  • Door surveys
  • Fire alarm installation
  • Erection of hoarding
  • Relocation of CCTV

June 2021 Weekly Updates

W/C 28th June:

  • Fire alarm installation
  • Drainage repairs
  • Erection of hoarding
  • Relocation of CCTV

Fire Door survey

W/C 21st June:

  • Erection of hoarding
  • Door surveys
  • Relocation of CCTV
  • Installation of external fire alarm
  • Remedial works to PV panels
  • Fire door survey’s

W/C 14th June:

  • Roof surveys – PV panels

W/C 7th June:

  • Erection of scaffold and heras fencing
  • Brick tie investigations – will involve the localised removal of brick work
  • Pedestrian access will be diverted while these works are carried out

May 2021 Weekly Updates

W/C 31st May:

  • Erection of scaffold and heras fencing.
  • Pedestrian access will be diverted while these works are carried out

W/C 24th May:

  • Erection of mastclimbers, scaffold and heras fencing.
  • Pedestrian access will be diverted while these works are carried out
  • PE roof survey

W/C 17th May:

  • Erection of mastclimbers, scaffold and heras fencing.
  • Pedestrian access will be diverted while these works are carried out
  • Installation of site generator
  • Works to roof PV panels

W/C 10th May:

  • Pick Everard roof survey

W/C 3rd May:

  • Brick tie surveys and pull out tests to slab edge

April 2021 Weekly Updates:

W/C 26th April:

  • Brick tie surveys and pull out tests to slab edge
  • 7 Day Notification: PV Electrical Works

W/C 19th April:

  • 3D Surveys Flats & Communal areas
  • CCTV drainage surveys *
  • Site set up letter

* Please note these works will involve increased levels of noise due to the associated drilling, grinding and hammering.

W/C 12th April:

  • Waterproofing to all elevation top four floors

W/C 5th April:

  • Internal fire alarm surveys
  • Waterproofing to all elevation top four floors / Lift housing fascia fixings
  • Brick tie surveys to all elevations and all levels

March 2021 Weekly Updates

W/C 29th March:

  • Waterproofing to all elevation top four floors
  • Brick tie surveys to all elevations and all levels

W/C 22nd March:

  • Waterproofing to all elevation top four floors
  • Brick tie surveys to all elevations and all levels
  • RPS survey to staff kitchen & adjoining store
  • Apply mastic seal to doors and windows following brick slip removal
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Waterproofing to all elevation on the top four floors.
  • Brick tie surveys to all elevations and all levels.
  • Roof condition survey by Pick Everard.
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 8th March:

  • Brick tie surveys to all elevations and all levels.
  • Apply mastic seal to doors and windows following brick slip removal
  • 7 Day Notice Letter – External inspections and weather proofing works

W/C 1st March:

  • Brick tie surveys to all elevations and all levels
  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal.

Febuary 2021 Weekly Updates

W/C 22nd February:

  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal

W/C 15th February:

  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 8th February:

  • Apply mastic seal to doors and windows following brick slip removal

W/C 1st February:

  • Apply mastic seal to doors and windows following brick slip removal.
  • RPS external surveys

January 2021 Weekly Updates

W/C 25th January:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Lift housing surveys – PE & Windtec

W/C 14th December

  • Asbestos surveys to communal areas
  • Brick slip removal
  • Removal and refitting of bulkhead lights
  • External window pod surveys

W/C 7th December

  • Asbestos surveys to communal areas
  • External window pod surveys

November 2020 Weekly Updates

W/C 30th November

  • Surveys to communal areas
  • External window pod surveys
  • Brick slip investigation and planning

W/C 23rd November

  • Surveys to communal areas
  • External window pod surveys
  • Flat 12 (void) – making good works following survey and hand back
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • Surveys to communal areas
  • External window pod surveys
  • Flat 12 – surveys
  • Internal surveys, communal areas
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Concrete testing, floor slabs – will involve drilling

W/C 9th November

  • Surveys to communal areas
  • Flat 114 – making good works
  • Flat 12 – enabling works, this will involve drilling and hammering.
  • Internal surveys, communal areas – Argos
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Concrete testing, floor slabs – will involve drilling

W/C 2nd November

  • Surveys to communal areas
  • External surveys
  • Brick work remediation continues
  • Concrete testing of floor slabs

October 2020

W/C 26th October

  • External Surveys
  • Surveys in bin sotres, garages, plant rooms

September 2020

  • External surveys continue
  • Survey of lift housing antenna
Beech Court

Got any questions? Ask Paul, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updaters:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

15th November:

  • No updates this week

8th November:

  • Ground plate bearing tests

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • SCF pull out tests
  • SCF lift housing survey
  • PE – door surveys

W/C 18th October:

  • Truline door surveys
  • Grass cutting & litter pick
  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • No updates this week

September 2021 Weekly Updates:

W/C 27th September:

  • No updates this week

W/C 20th September:

  • Grass cutting and litter picking behind heras fencing

W/C 13th September:

  • No updates this week

W/C 6th September:

  • No updates this week

August 2021 Weekly Updates

W/C 31st August:

  • No updates this week

W/C 23rd August:

  • Removal of loose insulation from floor of pump room
  • Removal of loose insulation from floor from garage

W/C 16th August:

  • Ground investigation, sprinkler tank, core drilling in garage
  • Visual asbestos survey in pump room

W/C 9th August:

  • Visual asbestos survey of pump room

W/C 2nd August:

  • Door surveys, communal power required
  • Non intrusive visual sprinkler survey

July 2021 Weekly Updates

W/C 26th July:

  • Door surveys

W/C 19th July:

  • Grass maintenance
  • Installation of data units to PV’s

W/C 12th July:

  • Grass maintenance
  • PE Floor slab concrete testing
  • Capping strapping inspection

W/C 5th July:

  • Capping strapping inspection

June 2021 Weekly Updates

W/C 28th June:

  • Fire Door survey

W/C 21st June:

  • Remedial works to PV panels

W/C 14th June:

  • Roof surveys – PV panels
  • Door surveys

W/C 7th June 2021:

  • Brick tie investigations – will involve the localised removal of brick work
  • Brick tie surveys and pull out tests to slab edge
  • Door Surveys

May 2021 Weekly Updates

W/C 31st May:

  • Removal of scaffold
  • Brick tie surveys and pull out tests to slab edge

W/C 24th May:

  • Asbestos removal to garages
  • Brick tie surveys and pull out tests to slab edge

W/C 17th May:

  • Works to roof PV panels
  • Brick tie surveys and pull out tests to slab edge

W/C 10th May:

  • Works to roof PV panels
  • Pick Everard roof survey
  • Brick tie surveys and pull out tests to slab edge

W/C 3rd May:

  • Brick tie surveys and pull out tests to slab edge

April 2021 Weekly Updates

W/C 26th April:

W/C 19th April:

  • Brickwork surveys. *
  • CCTV drainage surveys *
  • 28 day notice – Asbestos removal letter

* Please note these works will involve increased levels of noise

W/C 12th April:

  • Internal 3D surveys – flats & communal areas

W/C 5th April:

  • No new updates this week

March 2021 Weekly Updates

W/C 29th March:

  • Site survey systems – external surveys

W/C 22nd March:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Site survey systems – external surveys
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Temporary strapping installation to roof cappings.
  • Apply mastic seal to doors and windows following brick slip removal.
  • External surveys by Site Survey Systems.
  • Roof condition survey by Pick Everard.
  • Wintech intrusive external surveys to all floors.

W/C 8th March:

  • Temporary strapping installation to roof cappings.
  • Apply mastic seal to doors and windows following brick slip removal.
  • Site survey systems – external surveys.

Wintech intrusive external surveys to all floors. 

W/C 1st March:

  • Temporary strapping installation to roof cappings
  • 7- day inspection of parapet cappings
  • Apply mastic seal to doors and windows following brick slip removal.

February 2021 Weekly Updates

W/C 22nd February:

  • Temporary strapping installation to roof cappings
  • Brick surveys
  • Concrete surveys to floor slab edge, will involve drilling
  • PTSG – lightening conductor tests
  • 7-day inspection of parapet cappings
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 15th February:

  • Temporary strapping installation to roof cappings
  • Brick surveys
  • Concrete surveys to floor slab edge, will involve drilling
  • PTSG – lightening conductor tests
  • Remedial groundworks commence

W/C 8th February:

  • Temporary strapping installation to roof cappings
  • Brick surveys
  • PTSG – lightening conductor tests
  • Remedial groundworks commence

W/C 1st February:

  • Lift housing surveys – PE & Windtec
  • Temporary strapping installation to roof cappings – all elevations
  • Brick surveys
  • ARD removals – Bulkstore, lift motor room & RPS inspections
  • PTSG – lightening conductor tests
  • Concrete testing – will involve drilling

January 2021 Weekly Updates

W/C 25th January:

  • Lift housing surveys – PE & Windtec
  • Temporary strapping installation to roof cappings – all elevations
  • Brick surveys
  • ARD surveys
  • PTSG – lightening conductor tests
  • Concrete testing – will involve drilling

W/C 4th January :

  • Surveys of communal areas by contractor RPS
  • Brick slip removal work

December 2020 Weekly Updates

W/C 14th December

  • Asbestos surveys to communal areas
  • External window pod surveys
  • Brick slip removal
  • Brick work remediation continues, this will involve drilling and grinding works.
  • Removal and refitting of bulkhead lights
  • Closure of gable facing Belvedere Road 8.00 to 17.00
  • Brickwork surveys

W/C 7th December

  • Asbestos surveys to communal areas
  • External window pod surveys
  • Brickwork surveys

November 2020 Weekly Updates

W/C 30th November

  • Surveys to communal areas
  • External window pod surveys
  • Brick slip investigation and planning

W/C 23rd November

  • Surveys to communal areas
  • External window pod surveys
  • Flat 38 – (void) making good after survey work and hand back
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • External window pod surveys
  • Flat 38 – PE surveys

W/C 9th November 

  • Flat 38 – enabling works, this will involve drilling and hammering./C 9th November

W/C 2nd November

  • Surveys to communal areas
  • External Surveys

October 2020

W/C 26th October

  • Surveys to bin stores, garages, plantrooms etc
  • Juliet balcony remediations

September 2020

W/C 14th September

  • Cladding removal continues
  • Removal of scaffold to gable and door canopies
  • Survey of lift housing antenna
Whitebeam Court

Got any questions? Ask Christine, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updaters:

22nd November:

  • Adaptions to scaffolding to allow access to the community room (potential)
  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering.

15th November:

  • Installation of temporary works to cables affecting all areas floors 10 & 11.
  • Adaptions to scaffolding to allow access to the community room (potential)

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

8th November:

  • Installation of temporary works to cables affecting all areas floors 10 & 11.

* These works will involve industry standard levels of noise due to the associated drilling, grinding and hammering

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • Alterations to scaffold to allow access to community room
  • PE – door surveys

W/C 18th October:

  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • Fire door survey

September 2021 Weekly Updates:

W/C 27th September:

  • Fire door survey

W/C 20th September:

  • External surveys PE

W/C 13th September:

  • Brick tie remedials testing

W/C 6th September:

  • No updates this week

August 2021 Weekly Updates

W/C 31st August:

  • Wall tie installation

W/C 23rd August:

  • Wall tie installation
  • Removal of loose insulation from floor of pump room

W/C 16th August:

  • Ground investigation, sprinkler tank, core drilling in future tank room
  • Visual asbestos survey in pump room
  • Limited slab edge testing of proposed façade bracket fixings
  • Access into sfs cavity to further inform the development of the design

W/C 9th August:

  • Limited slab edge testing of proposed façade bracket fixings
  • Access into sfs cavity to further inform the development of the design
  • Visual asbestos survey of pump room

W/C 2nd August:

  • Non intrusive visual sprinkler survey
  • Door surveys, communal power required

July 2021 Weekly Updates

W/C 26th July:

  • Door surveys

W/C 19th July:

  • Installation of data units to PV’s

W/C 12th July:

  • PE Floor slab concrete testing
  • Door surveys

W/C 5th July:

  • Door surveys

June 2021 Weekly Updates

W/C 28th June:

  • Fire Door survey

W/C 21st June:

  • Remedial works to PV panels
  • Fire door survey’s

W/C 14th June:

  • Roof surveys – PV panels

W/C 7th June:

  • Brick tie investigations – will involve the localised removal or brick work

May 2021 Weekly Updates

W/C 31st May:

  • No updates this week

W/C 24th May:

  • PE roof survey
  • Works to roof PV panels

W/C 17th May:

  • Works to roof PV panels

W/C 10th May:

  • Pick Everard roof survey

W/C 3rd May:

  • Brick tie surveys and pull out tests to slab edge

April 2021 Weekly Updates

W/C 26th April:

  • Brick tie surveys and pull out tests to slab edge
  • CCTV drainage surveys
  • 7 Day Notification: PV Electrical Works

W/C 19th April:

  • 3D Surveys Flats & Communal areas
  • Brickwork surveys. *

* Please note these works will involve increased levels of

W/C 12th April

  • No updates this week

W/C 5th April:

  • Internal fire alarm surveys
  • Brick tie surveys to all elevations and all levels

March 2021 Weekly Updates

W/C 29th March:

  • Brick tie surveys to all elevations and all levels

W/C 22nd March:

  • Brick tie surveys to all elevations and all levels
  • Apply mastic seal to doors and windows following brick slip removal.
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Brick tie surveys to all elevations and all levels.
  • Roof condition survey by Pick Everard.
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 8th March:

  • Brick tie surveys to all elevations and all levels.
  • Roof condition survey by Pick Everard.
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 1st March:

  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal.

February 2021 Weekly Updates

W/C 22nd February:

  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 15th February:

  • Brick repairs to ground floor – will involve drilling and grinding
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 8th February:

  • Apply mastic seal to doors and windows following brick slip removal

W/C 1st February:

  • Lift housing surveys – PE & Windtec
  • Apply mastic seal to doors and windows following brick slip removal.

January 2021 Weekly Updates

W/C 25th January:

  • Lift housing surveys – PE & Windtec
  • ARD surveys
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 4th January:

  • Surveys of communal areas by contractor RPS
  • Concrete testing – floor slab edge
  • Brickwork repairs to ground floor

December 2020 Weekly Updates

W/C 14th December

  • External Window pod surveys
  • EPDM repairs to nebe vents
  • Asbestos surveys to communal area
  • Installation of electrical supply ENWL – 4 parking spaces
  • Removal and refitting of bulkhead lights
  • Connection of temporary site lights to landlord’s supply
  • Brickwork repairs to ground floor

W/C 7th December

  • External window pod surveys
  • Repairs to nibe vents
  • Asbestos surveys to communal areas
  • Installation of electrical supply ENWL – 4 parking spaces still required
  • Brick slip removal

November 2020 Weekly Updates

W/C 30th November

  • External window pod surveys
  • Repairs to Nibe vents
  • Surveys to communal areas
  • Installation of electrical supply ENWL – 4 parking spaces required in he car park
  • Brick slip investigation and planning

W/ C 23rd November

  • Hoarding installation around scaffold
  • External window pod surveys
  • EPDM repairs to Nibe vents
  • Surveys to communal areas
  • Installation of electrical supply ENWL – 4 parking spaces needed in the car park
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • Hoarding installation around scaffold
  • External window pod surveys
  • EPDM repairs to Nibe vents
  • Surveys to communal areas
  • Concrete testing, floor slabs – will involve drilling
  • Installation of electrical supply ENWL – 4 parking spaces.

W/C 9th November

  • Hoarding installation around scaffold
  • Surveys to communal areas
  • Concrete testing, floor slabs – will involve drilling
  • Installation of electrical supply ENWL – 4 parking spaces required

W/C 2nd November 2020

  • Hoarding installation around scaffold
  • Surveys in communal areas
  • External Surveys
  • Brick work remediation continues
  • Concrete testing of floor slabs

October 2020

W/C 26th October

  • Hoarding installation around scaffold
  • Surveys in bin stores, garages, plant rooms etc
  • Brick work remediation continues
  • Roof caping survey
  • External surveys

Installation of electrical box

September 2020

W/C 14th September 

  • Cladding removal continues
  • Survey of lift housing antenna
  • Scaffold wagons will be on site
  • Scaffolding works continue
Holm Court

Got any questions? Ask Lisa, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

 

November 2021 Weekly Updaters:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.
  • Erection of scaffolding – this will involve drilling scaffolding ties into the floor slab edges and closure of the footpath to the gable facing Brotherton House until scaffold complete.

15th Novemver:

  • Erection of scaffolding – this will involve drilling scaffolding ties into the floor slab edges

8th November:

  • Ground plate bearing tests

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • SCF pull out tests
  • SCF lift housing survey
  • PE – door surveys

W/C 18th October:

  • Truline door surveys
  • Grass cutting & litter pick
  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • No updates this week

September 2021 Weekly Updates:

W/C 27th September:

  • No updates this week

W/C 20th September:

  • Grass cutting and litter picking behind heras fencing

W/C 13th September:

  • No updates this week

W/C 6th September:

  • No updates this week

August 2021 Weekly Updates

W/C 31st August:

  • No updates this week

W/C 23rd August:

  • Removal of loose insulation from floor of pump room

W/C 16th August:

  • Visual asbestos survey in pump room

W/C 9th August:

  • Visual asbestos survey of pump room

W/C 2nd August:

  • Non intrusive visual sprinkler survey
  • Door surveys, communal power required

July 2021 Weekly Updates

W/C 26th July:

  • No updates this week

W/C 19th July:

  • Grass maintenance
  • Installation of data units to PV’s

W/C 12th July:

  • Grass maintenance
  • Door surveys

W/C 5th July:

  • No updates this week

June 2021 Weekly Updates

W/C 28th June:

  • No updates this week

W/C 21st June:

  • Brick tie investigations – will involve the localised removal of brick work.
  • Will require closure of parking spaces to allow MEWP access

W/C 14th June:

  • Door surveys
  • Roof surveys – PV panels
  • Brick tie investigations – will involve the localised removal of brick work.

W/C 7th June:

  • No updates this week

May 2021 Weekly Updates:

W/C 31st May:

  • No updates this week

W/C 24th May:

  • No updates this week

W/C 17th May:

  • No updates this week

W/C 10th May:

  • Pick Everard roof survey

W/C 3rd May:

  • Works to roof PV panels

April 2021 Weekly Updates

W/C 26th April:

  • Brickwork surveys
  • CCTV drainage surveys
  • 7 Day Notification: PV Electrical Works

W/C 19th April:

  • 3D surveys flats & communal areas

W/C 12th April

  • No updates this week

W/C 5th April

  • No new updates this week

March 2021 Weekly updates

W/C 29th March:

  • No new updates this week

W/C 22nd March:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Brick / brick tie surveys
  • Closure of 2no parking space will be required to allow machine access as previously
  • Closure of pedestrian access Brotherton gable – 8am- 5pm. Full time banksman in attendance
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Brick surveys & brick repairs.
  • Closure of 2 car parking spaces will be required to allow machine access as previously.
  • Wintec intrusive external surveys to all floors.
  • Temporary strapping installation to roof cappings
  • External surveys by Site Survey Systems.
  • Roof condition survey by Pick Everard.
  • Closure of pedestrian access Brotherton gable 8am-5pm. Full time banksman in attendance

  W/C 8th March:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Brick surveys & brick repairs.
  • Closure of 2 car parking space will be required to allow machine access as previously.
  • Wintec intrusive external surveys to all floors.
  • Temporary strapping installation to roof cappings.
  • Site survey systems – external surveys.

Closure of pedestrian access to Brotherton gable – 8am- 5pm. Full time banksman in attendance.           

W/C 1st  March:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Brick surveys & brick repairs
  • Closure of 2no parking space will be required to allow machine access as previously
  • Wintec external surveys
  • Temporary strapping installation to roof cappings
  • 7-day inspection of parapet cappings
  • Closure of pedestrian access Brotherton gable – 8am- 5pm. Full time banksman in attendance

February 2021 Weekly Updates

W/C 22nd February:

  • Apply mastic seal to doors and windows following brick slip removal.
  • Concrete surveys to floor slab edge, will involve drilling
  • Brick surveys & brick repairs
  • Closure of 2no parking space will be required to allow machine access as previously
  • Remedial groundworks commence
  • Temporary strapping installation to roof cappings
  • 7-day inspection of parapet cappings
  • Closure of ped access Brotherton gable – 8am- 5pm. Full time banksman in attendance

W/C 15th February:

  • Flat 15 – making good
  • Concrete surveys to floor slab edge, will involve drilling
  • Brick surveys & brick repairs
  • Remedial groundworks commence
  • Temporary strapping installation to roof cappings – all elevations
  • Closure of ped access Brotherton gable – 8am- 5pm. Full time banksman in attendance

W/C 8th February:

  • Flat 15 – enabling works for surveys
  • Brick surveys & brick repairs
  • Remedial groundworks commence
  • Temporary strapping installation to roof cappings – all elevations
  • Closure of ped access Brotherton gable – 8am- 5pm. Full time banksman in attendance

W/C 1st February:

  • Lift housing surveys – PE & Windtec
  • RPS external surveys
  • Flat 15 – enabling works for surveys
  • Brick surveys & brick repairs
  • PTSG – lightening conductor tests
  • Temporary strapping installation to roof cappings – all elevations
  • Closure of ped access Brotherton gable – 8am- 5pm. Full time banksman in attendance

January 2021 Weekly Updates

W/C 25th January:

  • Lift housing surveys – PE & Windtec
  • ARD surveys
  • Brick surveys & brick repairs
  • PTSG – lightening conductor tests
  • Temporary strapping installation to roof cappings – all elevations
  • Closure of ped access Brotherton gable – 8am- 5pm. Full time banksman in attendance

W/C 11th Janaury

No further updates

W/C 4th January:

  • Surveys of communal areas by contractors RPS
  • Brickwork surveys

December 2020 Weekly Updates 

W/C 14th December 

  • External window pod surveys
  • Asbestos survey to communal areas

W/C 7th December

  • External window pod surveys
  • Asbestos surveys to communal areas

November 2020 Weekly Updates

W/C 30th November

  • External window pod surveys
  • Surveys to communal areas
  • Brick slip investigation and planning

W/C 23rd November

  • External window pod surveys
  • Surveys to communal areas
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • External window pod surveys

W/C 9th November

No further updates for Holm Court this week

W/C 2nd November

  • Surveys in communal areas
  • External Surveys

October 2020

W/C 26th October

  • Surveys in bin stores, garages, platrooms etc
  • External Surveys

September 2020

W/C 14th September

  •  Cladding removal continues
  • Closure of gable end facing The Gateway
  • Survey of lift housing antenna
  • Removal of uplighters
  • Structural survey
  • Expert witness filming
Plane Court

Got any questions? Ask Emily, 0300 555 5567, PendletonRLO@togetherhousing.co.uk

 

November 2021 Weekly Updates:

22nd November:

  • RPS surveys & sampling of plant/tank rooms, risers, binstores.

15th November:

  • No updates this week

8th November:

  • Ground plate bearing tests

1st November:

  • PE – door surveys

October 2021 Weekly Updates:

W/C 25th October:

  • PE – door surveys

W/C 18th October:

  • Grass cutting & litter pick
  • PE – door surveys

W/C 11th October:

  • PE – door surveys

W/C 4th October: 

  • No updates this week

September 2021 Weekly Updates:

W/C 27th September:

  • No updates this week

W/C 20th September:

  • Grass cutting and litter picking behind heras fencing

W/C 13th September:

  • No updates this week

W/C 6th September:

  • No updates this week

August 2021 Weekly Updates

W/C 31st August:

  • No updates this week

W/C 23rd August:

  • No updates this week

W/C 16th August:

  • No updates this week

W/C 9th August:

  • No updates this week

W/C 2nd August:

  • Non intrusive visual sprinkler survey
  • Door surveys, communal power required

June 2021 Weekly Updates

W/C 26th July:

  • Door surveys

W/C 19th July:

  • Installation of data units to PV’s
  • Door surveys

W/C 12th July:

  • No updates this week

W/C 5th July:

  • Brick tie investigations – will involve the localised removal of brick work.

W/C 28th June:

  • No updates this week

W/C 21st June:

  • Brick tie investigations – will involve the localised removal of brick work.

W/C 14th June:

  • Roof surveys – PV panels
  • Brick tie investigations – will involve the localised removal of brick work.

W/C 7th June:

  • No updates this week

May 2021 Weekly Updates:

W/C 31st May:

  • Fire Door Surveys

W/C 24th May:

  • PE internal survey of risers/service cupboards
  • Intrusive survey of flat 30 window pod
  • Door surveys

W/C 17th May:

  • Fire Door Surveys

W/C 10th May:

  • Pick Everard roof survey

W/C 3rd May:

  • Works to roof PV panels

April 2021 Weekly Updates

W/C 26th April:

  • Brickwork surveys
  • CCTV drainage surveys
  • 7 Day Notification: PV Electrical Works

W/C 19th April:

  • Concrete testing to floor slab edge. *
  • External survey, removal of localised sections of Cembrit to photograph and measure. *
  • Steel & SFS, board to be replaced and resealed.

* Please note these works will involve increased levels

W/C 12th April:

  • Concrete testing to floor slab edge
  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed

W/C 5th April:

  • Internal 3D surveys
  • Concrete testing to floor slab edge elevations A&B
  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed

March 2021 Weekly Updates

W/C 29th March:

  • External survey, removal of localised sections of cembrit to photograph and measure steel & SFS, board to be replaced and resealed

W/C 22nd March:

  • Temporary strapping installation to roof cappings
  • Apply mastic seal to doors and windows following brick slip removal
  • CCTV Drainage Survey Letter
  • Fire Door & Pre Entry Survey Letter

W/C 15th March:

  • Temporary strapping installation to roof cappings.
  • Flat 30 – reinstatement works – Truline.
  • Roof condition survey by Pick Everard.
  • Apply mastic seal to doors and windows following brick slip removal.

W/C 8th March:

  • Temporary strapping installation to roof cappings.
  • Install access hatch in communal area outside Flat 30.
  • Apply mastic seal to doors and windows following brick slip removal.
  • 28 Day Notice Letter – 3D Surveys in Communal Areas

W/C 1st March:

  • Temporary strapping installation to roof capping
  • Flat 30 – PE surveys potentially external investigation at the property
  • Apply mastic seal to doors and windows following brick slip removal.

February 2021 Weekly Updates

W/C 22nd February:

  • RPS external surveys
  • PTSG – lightening conductor tests
  • Apply mastic seal to doors and windows following brick slip removal.
  • Remedial groundworks commence

W/C 15th February:

  • RPS external surveys
  • PTSG – lightening conductor tests
  • Remedial groundworks commence

W/C 8th February:

  • RPS external surveys
  • PTSG – lightening conductor tests
  • Remedial groundworks commence
  • Brick slip removal to front elevation

W/C 1st February:

  • RPS external surveys
  • PTSG – lightening conductor tests
  • Lift housing surveys – PE & Windtec

January 2021 Weekly Updates

W/C 25th January: 

  • ARD surveys
  • PTSG – lightening conductor tests
  • Lift housing surveys – PE & Windtec

W/C 11th January:

  • No further updates this week

W/C 4th January:

  • Surveys of communal areas by contractors RPS
  • Brickwork surveys

December 2020 Updates

W/C 14th December

  • External window pod surveys
  • Asbestos survey to communal areas
  • Capping inspection – Wintech

W/C 7th December 

  • External window pod surveys
  • Asbestos surveys to communal areas
  • Internal surveys of live flats – 38,65 &76
  • Asbestos removal lift motor room core 4 – Friday. All affected residents have now been contacted

November 2020 Weekly Updates

W/C 30th November

  • External window pod surveys
  • Surveys to communal areas
  • Flat 63 void property – enabling works an dsurvey
  • Brick slip investigation and planning

W/C 23rd November

  • External window pod surveys
  • Surveys to communal areas
  • Capping investigation & planning
  • Brick slip investigation and planning

W/C 16th November

  • External window pod surveys
  • Flat 34 – making good works following survey

 W/C 9th November

  • Flat 34 – making good works following survey

W/C 2nd November

  • Surveys in communal areas
  • External surveys

October 2020

W/C 26th october

September 2020

W/C 14th September

Share This